What This File Appears To Be

Exhibit A: Contractor Documents Irene ESTIMATE Contractor is being hired by B2B Property Management Est. #: 9143 Date: 3/7/2023 on behalf of the property owner Valid for 30 days Project Address: 9902 Garfield Pricing includes parts and labor INSPECTION ITEM # ITEM DESCRIPTION UNITS TOTAL PRICE / UNIT Item # General Requirements Interior/Exterior 1 $ - $ 250.00 Item # Trash. Paint chip removal pre-clean Exterior 1 $ - $ 250.00 Note Hazards found on the exterior f the house subject to LHCO are not

Text Preview

Exhibit A: Contractor Documents

Irene

ESTIMATE

Contractor is being hired by B2B Property Management

Est. #:

9143

Date:

3/7/2023

on behalf of the property owner

Valid for 30 days

Project Address: 9902 Garfield

Pricing includes parts and labor
INSPECTION ITEM #

ITEM DESCRIPTION

UNITS

TOTAL

PRICE / UNIT

Item #

General Requirements Interior/Exterior

1

$

-

$

250.00

Item #

Trash. Paint chip removal pre-clean Exterior

1

$

-

$

250.00

Note

Hazards found on the exterior f the house subject to LHCO
are not part of this quote (LHCO attached)

1

$

-

$

-

1

$

-

$

-

Interior

All holes in plaster walls up/down

1

$

-

$

350.00

Item #

trash removal interior

1

$

-

$

2,200.00

Item #

Living RM mantel replace missing glass

1

$

-

$

225.00

Item #

Dining RM replace electrical outlet

1

$

-

$

75.00

Item #

ining RM closet cleanout replace/cover lower walls
paneling

1

$

-

$

450.00

1

$

-

$

-

1

$

-

$

235.00

1

$

-

$

-

Item #

thermostat installation

Item #

Kitchen Paint complete

1

$

-

$

966.00

Item #

Kitchen Window glass replace

1

$

-

$

250.00

1

$

-

$

-

1

$

-

$

1

$

-

$

-

Item #

Basement paintfilm stabilization all walls and supporting
beams

2,700.00

Item #

Replace Furnace filter

1

$

-

$

25.00

Item #

secure chimney door

1

$

-

$

50.00

Item #

secure electrical hazard in basement

1

$

-

$

100.00

1

$

-

$

-

Owner’s Initials: ________ Contractor’s Initials: ________ Project Manager’s Initials: ________

INSPECTION ITEM #

ITEM DESCRIPTION

UNITS

TOTAL

PRICE / UNIT

Item #

paint hallway leading upstairs 2nd floor

1

$

-

$

225.00

Item #

Paint Bedroom 1,2,3, LR, DR, Bath foyer complete

1

$

-

$

1,800.00

1

$

-

Item #

repair light in closet bed 3

1

$

-

$

125.00

Item #

install access panel in attic

1

$

-

$

150.00

Item #

install access panel in bathroom

1

$

-

$

75.00

Item #

install sink in bathroom

1

$

-

$

425.00

Item #

Repair electrical hazard in bathroom

1

$

-

$

125.00

Item #

replace leaky faucet bathtub

1

$

-

$

350.00

SUBTOTAL

$

11,401.00

B2B PM

$

570.05

TOTAL

$ 11,971.05

Memo: Contractor shall furnish any and all permits required for the completion of the project. Pricing includes
charges for labour and materials. Additional charges, deviation, or emergency repairs must be approved in
writing by Owner. Contractor certifies having proper insurance coverage to carry out the project. B2B Property
Management is acting as a project manager agent and shall not be held liable for any of the performance or
quality of the work performed by contractor, nor for any delays in payment, or other failures of property owner
to perform on its contractual duties and obligations.
Owner’s Initials: ________ Contractor’s Initials: ________ Project Manager’s Initials: ________