Crawford Construction Estimate 3495 - 2024-09-24 - Mold Remediation Turn Proposal - 9634 S Green St - 9634 S Green St, Chicago, IL 60643.pdf

This page is a searchable text preview. Use the Dropbox link for the full original file.

Open full file in Dropbox

Property9634 S Green St, Chicago, IL 60643
FolderRepairs & Maintenance
KindPDF
Updated2024-10-19
Dropbox path08 - Repairs & Maintenance/Crawford Construction Estimate 3495 - 2024-09-24 - Mold Remediation Turn Proposal - 9634 S Green St - 9634 S Green St, Chicago, IL 60643.pdf

What This File Appears To Be

Crawford Construction Corp. Estimate 5113 S Harper Ave Chicago, IL, 60615-4119 Estimate No: 3495 Date: 09/24/2024 info@crawfordconstructioncorp.net www.crawfordconstructioncorp.net 312.229.0134 For: Home River Group LLC 9100 Keystone Crossing STE 610 Indianapolis, IN 4624 1 WO#: TPPLNR3 - Address: 9634 S Green St, Chicago, IL 60643 2 Turn Proposal Code Description Mold Remediation HEPA Vacuuming w/ (Fogging/Duct Cleaning) - Detailed - (PER SF) - 985.00 SF - Optional: Includes: Equipment and labo

Text Preview

Crawford Construction Corp.

Estimate

5113 S Harper Ave
Chicago, IL, 60615-4119

Estimate No:

3495

Date:

09/24/2024

info@crawfordconstructioncorp.net
www.crawfordconstructioncorp.net
312.229.0134

For:

Home River Group LLC
9100 Keystone Crossing STE 610
Indianapolis, IN 4624

1

WO#: TPPLNR3 - Address: 9634 S Green St, Chicago, IL 60643

2

Turn Proposal

Code

Description

Mold Remediation

HEPA Vacuuming w/ (Fogging/Duct Cleaning) - Detailed - (PER SF) - 985.00 SF

- Optional:

Includes: Equipment and labor to vacuum. Detailed HEPA vacuuming.

Quantity

Rate

Amount

985

$1.75

$1,723.75

1

$725.00

$725.00

Quality: Medium size back pack or canister type HEPA vacuums.
Notes: Normally used in a water/contamination clean-up situation where airborne mold
spores, etc. are present, but may also be used for other applications (soot or dust
removal,
etc.). Fogging treatment of the entire living space, at the reference location: Work will be
performed per task, as
described below:
- Workers to wear the appropriate PPE while performing the treatment in the
crawlspace
area
- Fog the entire home using a ULV sprayer with an EPA
- Registered Disinfectant
โ€“ Owners would need be out for 4-6 hours (estimated time)
3. HEPA vacuum all debris in the living room and kitchen. Wipe down wall surfaces in the
living room with an EPA registered anti microbial application.
Mold Remediation
- Optional:

Air Clearance Testing - Contamination - air or surface testing & lab analysis - 1.00 EA
Notes: Includes recommendation if the results return with elevated levels.

1/5

Crawford Construction Corp. - Estimate 3495 - 09/24/2024
Code

Description

Plumbing:

Sewer clean-out - 6" diameter - 1.00 EA

Quantity

Rate

Amount

1

$950.00

$950.00

1

$925.00

$925.00

Includes: 6" diameter sewer cleanout, 3 connectors, and installation labor.
Excludes: Riser and cap, excavation and backfill.
Quality: 6" diameter cast iron or PVC cleanout.
NOTES: Install clean out to toilets stack, that does not exist.
Plumbing:

Snake/Unclog Main Sewer Line w/ Camera Line Inspection - 1.00 EA
Includes: Heavy Duty Automatic Auger Drain Cleaning Machine w/ Operator: 3 in to 4 in
Drain Line I.D. Size Range, 100 ft Max. Run, 1/4" to 1โ€.

HVAC:

Furnace or A/C - check, clean, replace filters and service 1.00 EA

1

$275.00

$275.00

Cabinetry -

Up to 36" Vanity W/Top & Faucet - Complete Assembly - 1.00 EA

1

$605.50

$605.50

Bathroom:

The existing is damaged due from water & neglect and requires replacement.

Drywall Finishes:

1/2" water rock (greenboard) hung, taped ready for texture - 101.00 SF

101

$2.75

$277.75

1

$2,325.00

$2,325.00

1

$650.00

$650.00

Includes: Drywall, metal corner bead, joint compound (mud), drywall nails, joint tape,
grabber screws, and installation labor. Labor cost to remove 1/2" drywall, including
screws and/or nails, corner bead, and to discard in a job-site waste receptacle.
Quality: 1/2" water resistant drywall hung, taped, not including texture.
Shower Finishes:

Tile shower - 101 to 120 SF - 1.00 EA
Includes: Ceramic tile, grout, thinset, radius trim piece/bullnose, tile soap dish, the use of
a ceramic tile saw, and installation labor. Labor cost to remove ceramic tile and to discard
in a job-site waste receptacle.
Excludes: Shower pan or mortar bed for the tile.

Reglazing Fixture:

Refinish bathtub - 1.00 EA
Includes: Cleaning solution, etching chemical, bonding agent, primer, standard top-coat
colors, sand paper and labor to refinish a standard bathtub.
Excludes: Non standard colors.
Quality: Aliphatic acrylic polyurethane coating for a standard white 5' steel, porcelain,
cast iron with baked on enamel, or fiberglass bathtub.
Notes: Intended for resurfacing a tub with minor chip repair.

Flooring:

Stretch Carpet and Pad to Track Strip - 1.00 EA

1

$225.00

$225.00

Electrical:

Central air - Disconnect box - Up to 60 amp - non fused - 1.00 EA

1

$375.00

$375.00

13

$19.61

$254.93

6

$175.50

$1,053.00

Includes: Exterior-mount disconnect box and installation labor. Labor cost to remove a
disconnect box and to discard in a job-site waste receptacle.
Handrail(s) - Stairs
& Halls

Stairway:

Handrail - round / oval - hardwood - wall mounted
Includes: Handrail, bracket hardware, and installation labor
Stairway - Step - treated riser and treads (per tread) Up to 4' - 1.00 EA
Notes: Repair broken step at deck in three locations, patio door, left and right elevations.

2/5