Property84 Madison Ave, Albany, NY 12202
FolderRepairs & Maintenance
KindPDF
Updated2025-03-28
Dropbox path08 - Repairs & Maintenance/Daily Rehab Summaries and Invoices 2025-03-11 to 2025-03-27 - 84 Madison Ave, Albany, NY 12202.pdf

What This File Appears To Be

84 Madison Rehab 3/11/25 84 madison 2 hrs @$45/hr Evan 4 hrs @$95/hr Wess 4 hrs @$75/hr Zohar Total $770 Summary: 84.2: pre measurements for thresholds and placement as well as the remaining treads of the stair case. More painting of the trims and moving around of placement. The vanity in the bathroom is fully operational and placed now. Just need to finish the other bathroom accessories for bathroom to be done. Putting this separate because it's too much of a mix to figure out what with what. 5

Text Preview

84 Madison Rehab
3/11/25
84 madison
2 hrs @$45/hr Evan
4 hrs @$95/hr Wess
4 hrs @$75/hr Zohar
Total $770
Summary:
84.2: pre measurements for thresholds and placement as well as the remaining treads of the
stair case. More painting of the trims and moving around of placement. The vanity in the
bathroom is fully operational and placed now. Just need to finish the other bathroom
accessories for bathroom to be done.
Putting this separate because it's too much of a mix to figure out what with what.
5 hrs @$20/hr Jasmine
Total $100
This was spent doing a variety of work around the many buildings. Some to setup 86.2, some to
clean 88.0 of the mess, 84.2 work and etc.
3/12/25
84 madison
1 hr @$45/hr
2 hrs @$75/hr Zohar
4.5 hrs @$95/hr Wess
Total $622.50
Summary:
84.2: floor preparations in landings and placement of transitions, more painting and preparations
for getting kitchen counter top cut and placement for sink and etc
3/13/25
84 madison
1 hr @$45/hr Evan
4 hrs @$75/hr Zohar
6 hrs @$95/hr Wess
10 hrs @$20/hr Jasmine
Total $1065 (1115 - 50 cashback)
Summary:
Finish support for stairs on 3rd flight, cuts for treads of those stairs, more flooring on landings,
painting, preparations for furnishings
84 madison
6 hrs @$75/hr Zohar
7 hrs @$95/hr Wess
Total $1115
Summary:
Mounting of treads and adjusting stairs, reviewing roof for plans for rear egress for 3rd floor and
roof repairs

3/17/25
84 madison
6 hrs @$75/hr Zohar
4.5 hrs @95/hr Wess
Total $877.50
Summary:
I had stopped in but I got an amalgamation of updates since last week. I think this was for
washer and dryer hookups, garbage disposal switch, checking drains for washer, closet shelves,
etc
3/18/25
84 madison
8 hrs @$45/hr Evan
8 hrs @$75/hr Zohar
2 hrs @$20/hr Nico
Total $1000
Summary:
Furnishings, clearing up of space, making piles for returns, thresholds put in place, preparations
for railing for 3rd flight of stairs, rough preparations for kitchen countertops
3/19/25
84 madison
8 hrs @$45/hr Evan
4.5 hrs @$75/hr Zohar
1 hr @$20/hr Jasmine
Total $317.50 (=717.50 -400 withdrawal)
Summary:
More furnishings, mounting brackets in place for tv, cabinets being finished up, preparations to
close up the closets, preparations to seal and caulk the rest of the stairs that need it, do another
coat of paint for the trims (crown, base and etc) in stairway, made additional material savings
and returned them, washer was not acting like it should and I had repaired it since I diagnosed
the problem as it happened and I heard it
3/20/25
84 madison
6 hrs @$45 Evan
7 hrs @$75/hr Zohar
Total $795
Summary:
Got the mounts for tv on the walls. Gonna program the tvs together first then put them up.
Closet shelves repaired or made with hanging rods. We got the door repaired for the front closet
and got new ones cut for the other two rooms which we will mount tomorrow. Got ceiling painted
now in unit. Will be preparing to mount the room doors tomorrow for the bedrooms after we
removed more stuff and get things ready in unit.
3/21/25
6.75 hrs @$45/hr Evan