← 84 Madison Ave, Albany, NY 12202 · Portfolio index

Daily Rehab Summaries and Invoices 2025-03-11 to 2025-03-27 - 84 Madison Ave, Albany, NY 12202.pdf

Generated 2026-07-15T18:19:12.115766+00:00 from live Dropbox Public folders.

Property84 Madison Ave, Albany, NY 12202
Source property label84 Madison Ave, Albany, NY 12202
Section08 - Repairs & Maintenance
Categorypdf
Relative path08 - Repairs & Maintenance/Daily Rehab Summaries and Invoices 2025-03-11 to 2025-03-27 - 84 Madison Ave, Albany, NY 12202.pdf
Modified UTC2025-03-28T16:10:15.0000000Z
Size bytes83825
Extraction methodpdftotext-incremental

Description

84 Madison Rehab 3/11/25 84 madison 2 hrs @$45/hr Evan 4 hrs @$95/hr Wess 4 hrs @$75/hr Zohar Total $770 Summary: 84.2: pre measurements for thresholds and placement as well as the remaining treads of the stair case. More painting of the trims and moving around of placement. The vanity in the bathroom is fully operational and placed now. Just need to finish the other bathroom accessories for bathroom to be done. Putting this separate because it's too much of a mix to figure out what with what. 5

Extracted Content

84 Madison Rehab 3/11/25 84 madison 2 hrs @$45/hr Evan 4 hrs @$95/hr Wess 4 hrs @$75/hr Zohar Total $770 Summary: 84.2: pre measurements for thresholds and placement as well as the remaining treads of the stair case. More painting of the trims and moving around of placement. The vanity in the bathroom is fully operational and placed now. Just need to finish the other bathroom accessories for bathroom to be done. Putting this separate because it's too much of a mix to figure out what with what. 5 hrs @$20/hr Jasmine Total $100 This was spent doing a variety of work around the many buildings. Some to setup 86.2, some to clean 88.0 of the mess, 84.2 work and etc. 3/12/25 84 madison 1 hr @$45/hr 2 hrs @$75/hr Zohar 4.5 hrs @$95/hr Wess Total $622.50 Summary: 84.2: floor preparations in landings and placement of transitions, more painting and preparations for getting kitchen counter top cut and placement for sink and etc 3/13/25 84 madison 1 hr @$45/hr Evan 4 hrs @$75/hr Zohar 6 hrs @$95/hr Wess 10 hrs @$20/hr Jasmine Total $1065 (1115 - 50 cashback) Summary: Finish support for stairs on 3rd flight, cuts for treads of those stairs, more flooring on landings, painting, preparations for f